Works adjustment of the industrial and civil sewage treatment plant of Arzignano

Period 11/2012 – 04/2013
Client: Acque Del Chiampo Spa - Amount of works $ 25’635’593’08 (€ 19'743'226.389)

Description of the activities
1 – Strengthening of civil line
Improve Civil capacity that, during rainy period, reaches values in the order of 24,000 – 25,000 m3 / d, with the need to spillway (authorized) in the Canal. New supply of wastewater from Paper Mill Chiampo (active since 2012).
Future contribution (from 2016) to the treatment plant (yet to be determined in which line of treatment) of the first rain water of open areas of the companies listed in Annex F of the PTA.
2 – Optimization of the industrial line
Rationalization of the No. 1 line of the oxidation sector (No. 6 tanks for a total of 56,000 m3) aimed at ensuring safety and energy saving. Tertiary treatment of effluent – Effluent Improvement of SST and Chrome quality. Reuse (partial) of the effluent of the civil line as civil service water for the plant.