Description of the activities
1 – Strengthening of civil line
Improve Civil capacity that, during rainy period, reaches values in the order of 24,000 – 25,000 m3 / d, with the need to spillway (authorized) in the Canal. New supply of wastewater from Paper Mill Chiampo (active since 2012).
Future contribution (from 2016) to the treatment plant (yet to be determined in which line of treatment) of the first rain water of open areas of the companies listed in Annex F of the PTA.
2 – Optimization of the industrial line
Rationalization of the No. 1 line of the oxidation sector (No. 6 tanks for a total of 56,000 m3) aimed at ensuring safety and energy saving. Tertiary treatment of effluent – Effluent Improvement of SST and Chrome quality. Reuse (partial) of the effluent of the civil line as civil service water for the plant.
Works adjustment of the industrial and civil sewage treatment plant of Arzignano
HomeDesign and Supervision Works adjustment of the industrial and civil sewage treatment plant of Arzignano
Period 11/2012 – 04/2013
Client: Acque Del Chiampo Spa - Amount of works $ 25’635’593’08 (€ 19'743'226.389)
Related Projects
-
Zalan is a concrete dam. Its typical cross section can be described as follows: • Height of the Dam: 24.50 m... -
The project interested about 9.5 km of major road (10.5 m width), from the current primary route S.S.128 with... -
Qaziawa is a concrete gravity dam. Its typical cross section can be described as follows: • Height of the Dam:... -
A Contracts for Preliminary and Detailed Design for the construction of a concrete gravity dam in the Region... -
Chami Rokhana dam is a mixed embankment-concrete dam. The embankment dam typical cross section can be... -
This infrastructure project preparation concerns the regional competitiveness of the Vicenza, Padua and Rovigo... -
Preliminary Design Executive Direction operational electrical and special systems -
New steel Bridge with one central bay for the connection between the riversides of Canal Grande in Venice. -
Projects Description Palik is a zoned embankment dam with impervious core. Its typical section presents... -
The project interested the link between the motorway toll gate at Piovene Rocchette (A31 highway) and the... -
In the Chioggia area, work to secure dumps has involved the former Val da Rio dump created between 1964 and... -
• Type of the dam: Embankment, with some concrete elements for ancillary works on left side. Length of the... -
Main features of the work: • catchment km² 103.67; • maximum stored volume m³ 7,808,360; • crest length m... -
The project concerns the demolition of the existing steel and concrete bridge with three longitudinal bays and... -
Overall coordination, collaboration in architectural design final and enforceable. Preliminary and final...